Helia | Your West End Sanctuary

30 October 2022

All earthworks are now complete, and the tower crane is now in place.

– All column footings in the basement are now complete.

– Basement Level 4 precast lift shaft panels are now installed.

– Basement Level 4 concrete slab is now complete.

– Formwork & reinforcement for our Basement Level 3 is already well underway.

Visit our project website for more information – www.heliawestend.com.au

Stay tuned for more progress updates!