Helia | Your West End Sanctuary
30 October 2022
All earthworks are now complete, and the tower crane is now in place.
– All column footings in the basement are now complete.
– Basement Level 4 precast lift shaft panels are now installed.
– Basement Level 4 concrete slab is now complete.
– Formwork & reinforcement for our Basement Level 3 is already well underway.
Visit our project website for more information – www.heliawestend.com.au
Stay tuned for more progress updates!