8 August 2023
Level 4 concrete slab is now poured.
Builders hoist lift is installed and operational.
Removal of back-props is progressing well.
Fit out for internal finishes has now started.
Installation of windows and doors has now started.
Formwork & reinforcement for final level 5 is progressing well.
Stay tuned for more progress updates.