Lumina Stones Corner
28 July 2025
Ground and Upper Ground Floors are complete.
Level 1 is expected to be complete by 1 September 2025.
Mechanical exhaust ducting for the car park levels has commenced.
Fire sprinkler installation in the car park levels has commenced.
The standby emergency generator has been installed.